I see that Summerhill View has gone way over budget as well - an additional £2.333m required on top of originally approved re-based budget of £12.572m. I suppose we should count ourselves lucky that it is only 18% over budget!!
However what we have got is a 60 bed care home. In round figures each bed space has cost £250,000. Given that Government already owned the site this seems an astronomical cost. Is this yet another triumph of form over function with the "cottagey" appearance, false chimney stacks, stone cladding etc?
All it needs is to be functional - the residents won't give a monkeys what it looks like.
A "full" explanation is here:
spfile (tynwald.org.im)
I would love to understand more about
"Failure of a key product component resulting in prolongation of the scheme." and "Changes instructed at a point in the project when all design issues should have been closed out resulting in contractual compensation events."
The changes instructed when design has finished seems to be a regular failing of Government and has the contractors rubbing their hands.